An industry body expects China’s data centers to need more than 6,000 diesel generator sets in 2026, and exports of large units already top 2025’s total.

WHY IT MATTERS

Developers planning new Chinese data centers face generator order books that run to October 2027 at Yuchai Marine and Genset Power, making backup power a scheduling constraint.

China’s data centers will need more than 6,000 diesel generator sets in 2026, worth over RMB10 billion, according to Jia Bin, secretary-general of the China Internal Combustion Engine Industry Association. He gave the forecast to CCTV in a report published on November 17, which also cited customs data: China exported 4,547 compression-ignition generator sets rated above 2 megavolt-amperes (MVA) in January to September 2026, already more than the 3,339 it shipped in all of 2025.

Units above 2 MVA are the main size used to keep AI data centers running when grid power fails, CCTV said. Jia expects supply and demand to stay tightly balanced in 2027. The full CCTV text, republished by the Chongqing news portal Hualong Net, opens by tying the generator shortage to a surge in data-center construction driven by AI.

Yicai Global, in an English report on November 18, described the 6,000 units as exports. CCTV and Securities Daily, in a report carried by Eastmoney, both present the figure as domestic data-center demand, and the customs total for exports so far this year is 4,547.

Generator and parts makers are booked into 2027 and 2028

At Guangxi Yuchai Marine and Genset Power (广西玉柴船电动力股份有限公司), the production line is running at full capacity, and orders for its high-power data-center models are booked through October 2027, deputy production head Jiang Yiqiang told CCTV. Chen Yue, deputy head of the company’s research center, said data-center sets must start within 10 to 15 seconds, far faster than ordinary generators.

The shortage reaches further up the supply chain. Xu Li, general manager of crankshaft maker Alfing Industrial Components (Guilin) (阿尔芬工业部件(桂林)有限公司), said its crankshaft orders for diesel generators are booked into 2028.

Securities Daily’s November 18 report added that Shandong Heavy Industry Group chairman Wang Zhijian told an investor day in early November that the group’s power energy business has orders booked to 2028, with fast growth in China and the US. Weichai Power’s third-quarter report showed sales of its M-series high-end engines, mainly used for power generation, above 11,000 units in the first nine months, up more than 40%. Within that, data-center generation products exceeded 2,700 units, up nearly 200%, with about 1,300 in the third quarter alone. Yicai Global cited a China Galaxy Securities report saying capacity at leading makers of high-power data-center generators is already scheduled through 2028.

Backup ratios are rising with each AI building

Buyers are adding more generators per site. Kang Nan, vice president of ZDATA (中联数据集团), told CCTV that the company’s purchases have risen to about 600 sets a year starting this year, and that he expects demand to grow at least 30% a year. A single 50,000-square-meter data center building now needs about 50 to 60 diesel generators, according to ZDATA.

Kaiyuan Securities, cited by Securities Daily, said advanced data centers now install generator capacity equal to 120% to 150% of need, up from 80% to 100% under traditional backup designs, turning generators from an optional item into standard equipment. Tianfeng Securities estimated that China’s AI computing build-out will require about 8,912 diesel generator sets in 2026 and 12,327 in 2027. Both figures are higher than Jia’s forecast of more than 6,000 sets for 2026.

Foreign suppliers offer little relief. Several international makers have already scheduled their high-power backup generator capacity through 2027 to 2028, Securities Daily reported, citing Kaiyuan Securities and company statements. Yicai Global framed the gap through electricity itself, writing that computing power is growing faster than power supply, which grows linearly.

Capacity additions are the next signal to watch

Suppliers are responding with new plants. Tianrun Industry, which makes engine parts, is running at full load and accelerating new capacity projects because existing lines are insufficient, Securities Daily said, and Shandong Heavy Industry is planning further capacity investment.

The industry’s numbers will be tested by two releases: China’s full-year customs figures for generator sets above 2 MVA, which will show whether exports keep rising after the 4,547 shipped by September, and Weichai Power’s full-year results, after its data-center generation sales nearly tripled in the first nine months.